Saturday, February 27, 2016
Thursday, February 18, 2016
Progress Report
To gauge how much progress is being made we have a 230
item task list of things we need to accomplish before we are all done. Some
tasks will take a few hours, some a few days. But, each time a job is complete
we check it off. The list is not all-encompassing, because we began it well
into our part of the project. But it is a great motivator. It feels wonderful to
add the little check marks. We missed a lot of tasks when the list was first made,
so we add to it when we think of those things. Even though the list grows
longer day by day, the check marks outpace the additions. Every few days we do
the math and see what percent of the project is done. Right now we are at 38%.
![]() |
| There are 40 tasks to be done for the main floor bathroom. We only have 7 left to go. |
![]() |
| It will take about five days to get just one check mark; "install wainscoting," perhaps by the end of the week. |
![]() |
| When it is installed, it may only take a day of work to check off "paint wainscoting." |
![]() |
| Finished this Tuesday. Repairing the cracks in the plaster walls and ceiling, and painting the ceiling and walls allowed us to check 3 things off. |
Friday, February 12, 2016
Not Our Favorite Job
We move ahead on two fronts; the main floor bathroom and the entryway. We're excited about the bathroom, as it is coming together beautifully. We have towels and washcloths already to move in, and hope to do so in a week or two.
The entry is a different story. There it is all about plaster repair. Sami has done some of the work, but Don has done much more.
The entry is a different story. There it is all about plaster repair. Sami has done some of the work, but Don has done much more.
![]() |
| NO fun! |
![]() |
| No fun at all. |
![]() |
| Keeping it out of the rest of the house is impossible. |
Thursday, February 4, 2016
Here, There, and Everywhere
We have been working hard. Every day we check off one or two
items from the to-do list. Don built and installed the trim around the two
custom kitchen built-ins, and Sami spent hours painting it all. When the time
finally came to put the shelves, drawers, and doors back on the cabinets, we
found that each drawer was a slightly different size (!*?!**!). That meant the drawers
would not fit into the trim on the bottom, and would not close all the way. So,
Don took the bottom drawers apart and made new faces for them. Then they had to
be primed and painted again. Now they fit, but it was a lot of extra work.
![]() |
| This cabinet is what became of our old "phone nook." |
![]() |
| This is the pantry that sits above the stairwell to the basement. |
To keep up with the projects we must buy more supplies every few days. Last Friday we spent time at Home Depot and Wink’s
Hardware deciding on kitchen drawer and door handles. At a glass shop we
ordered the window glass for the kitchen built-in and the privacy glass for the
bottom pane of the bathroom window, then another trip to the paint store for another gallon of primer, trim paint and sand paper. We are doing our best to keep the economy healthy.
![]() |
| These built-into-the-wall shelves are like the ones Don built in our upstairs bathroom |
The main floor bathroom window required a lot more work
than first anticipated. To make it right, Don has had to almost completely
rebuild it. He also spent time building both sets of shelves and the trim for
them, which gave Sami more work; painting, painting, painting.
![]() |
| Pretty soon the wainscoting can be added. |
As if that were not enough, Corey is back and he is laying a new cedar floor on the deck outside our living room. Don built the deck about 22 years ago and lately the wood has deteriorated badly. Luckily, the supports are all still in good shape, and did not need to be rebuilt.
![]() |
| Corey works in almost any weather. |
"Work hard, play hard."
We find that every so often it is time
for a much deserved Hammerhead.
Cheers!
Tuesday, January 26, 2016
Room (?) Number Three – DONE
It has taken a good two weeks of work, but the under-the-stairs coat closet is finally finished. In fact, it was taken so much work we have re-named it the “Coat Pavilion.” Before, it had one rod that stretched from just inside the door to the back of the closet, a little shelf above the rod, and two hooks on the back wall. Storage was awkward because the front part of the clothes rod was only a few inches from the wall, so coats hung at a funny angle, and hats, gloves, and scarves were always falling off of the too-narrow shelf.
The plaster walls were crisscrossed with big and little cracks. Patching the small cracks in the plaster was a many-step process of applying joint compound (mud) to the cracks, waiting for it to dry, sanding it, applying more mud, letting it dry, and sanding again. Medium cracks required and application of plaster repair fabric (Fiba tape), drying, sanding, and then more mud, etc., etc. The big cracks and the places where the plaster had pulled away from the wall required a patch system called “Big Wally’s” which was yet another multi-stage process and messy, but it worked well. The walls were very unevenly textured and the goal was to make the patched areas look like the rest of the wall.
Sami designed the new lay out, and Don built the new shelves and rods. Everything was primed and then painted. Don added new quarter round at the bottom edge and we gave the floor a coat of urethane. We also added an IKEA storage system with four pull-out mesh drawers.
![]() |
| Our favorite touch is the three owls who have taken up residence; Bubobubo, Hedwig and Pigwidgeon. |
We suppose a closet can not be called a “room.” But whatever it is, it is DONE!
Friday, January 22, 2016
Trim trim
We chug along, each of us working through the list of tasks.
As part of our project, we have both put in considerable amounts of time
getting layers of old paint off of existing wood trim. Often there were four
and five layers of paint and you had to know some of it had lead in it. We took
a vote, and it was unanimous – we decided to have all the trim left to be done “dip-stripped.”
:Last weekend Sami hauled the lot to “Timby’s” in
North Portland, and today we picked up the cleaned-of-paint trim. We saved
weeks of work, and enjoyed doing business with locals; Tim and Debby. Their
shop is filled with interesting furniture projects, Tim’s collection of vintage
tin cans (Which held at one time, everything from coffee to calves livers.),
and one very friendly little black and white doggie.
![]() |
| There is a lot of trim in our house! |
Wednesday, January 13, 2016
WHAT A DAY!
We made a list of all of the tasks left to be done, and its very daunting - 206 items long! But we continue to plow ahead. Besides making the list, we got three big items that have been long in the planning stages; the counter tops were installed,
Sami picked up the back splash tile from Pratt & Larson,
and we chose and purchased ceiling lights for the kitchen, and Don installed them.
We checked 4 items off of our list. How about that!?
![]() |
| It took the workers less than an hour to install the counters, but they did a great job. |
Sami picked up the back splash tile from Pratt & Larson,
![]() |
| Here are most of the figurative tiles that will form the mosaic behind the range. |
and we chose and purchased ceiling lights for the kitchen, and Don installed them.
![]() |
| The lowered ceiling is gone, so there is room for "school house" lights. |
We checked 4 items off of our list. How about that!?